Who Controls the Electric Transmission Grid?

Utilities Own Portions of the Electric Transmission Grid

Today’s electric transmission grid consists of 360,000 miles of high voltage transmission lines. While we often refer to a single grid, the following map shows that there are actually three transmission grids in the United States:

Source: energy.gov

Who controls these grids? And how do they ensure that the lights come on every time that we flip the switch?

A short time ago the answer would have been simple.  Your local utility owned and managed the portion of the electric transmission grid that interconnected its generating plants to its local distribution system. Your utility also owned and managed the portion of the electric transmission grid that interconnected its system with neighboring utilities (referred to as “inter-ties”). These inter-ties facilitated purchases and sales of wholesale power. Today the answer to the question of who controls the grid is not quite that simple.

The Northeast Power Blackouts

The old system of individual ownership and management of portions of the electric transmission grid had its weaknesses. Those weaknesses first became apparent in 1965 when a blackout of the Northeast United States left 30 million people without power. It turned out that the inter-ties between utilities enabled an outage on one portion of the electric transmission grid to lead to numerous successive outages on other portions.

In response to the 1965 Northeast Blackout the utility industry agreed that the utility-by-utility planning was not working. They promised to start planning their high voltage transmission systems on a regional basis. They also promised that they would voluntarily implement uniform reliability procedures.

The path to a reliable transmission grid was a little bumpy. The utilities did not all comply with the voluntary procedures and, in 1973, there was another major Northeast Power Blackout. In response to that second Blackout, in 2005, Congress passed legislation giving the Federal Energy Regulatory Commission (FERC) authority to enforce mandatory reliability standards. In 2006 FERC delegated responsibility for developing the mandatory reliable standards to the North American Electric Reliability Corporation (NERC).

The current electric transmission grid, developed as a result of the regional planning processes and compliance with mandatory reliability standards facilitates an electric grid that provides for reliable transmission of power over multiple utility systems.

The FERC’s Open Access Orders

The availability of reliable long distance transmission of electricity led policy makers to conclude that generation should be provided on a competitive, rather than regulated, basis. Therefore, in 1995 the Federal Energy Regulatory Commission (FERC) issued its Open Access Orders. Those Orders required every utility to provide non-discriminatory access to its high voltage transmission system. In effect, the FERC was turning the electric transmission grid into an interstate highway system where each utility would have to transport their own generation and the generation of others on a equal basis.

When it issued its Open Access Orders the FERC suspected that utilities could not be trusted to provide access on a non-discriminatory basis. They were concerned that utilities would favor their own generation at the expense of other parties’ generation.  The FERC was afraid that it would have to deal with a raft of complaints from generators who claimed that utilities were violating the non-discriminatory access provisions of the Open Access Orders.

Creation of the ISO/RTOs

In order to make sure that non-discriminatory access was actually achieved the FERC strongly urged utilities to turn control of their transmission facilities over to new entities called Independent System Operators (since renamed Regional Transmission Operators or ISO/RTOs). ISO/RTOs are non-profit entities whose members include utilities, generators and customers. The members elect an independent Board of Directors who manage the ISO/RTO staff.

Utilities that join an ISO/RTO retain ownership of their high voltage transmission facilities. But they operate those facilities at the direction of the ISO/RTO. The ISO/RTO is responsible for coordinating and directing the flow of electricity over its region’s high-voltage transmission system. The ISO/RTO also performs the studies, analyses, and planning to ensure regional reliability for future periods. As discussed in the Post entitled Electricity Sales in the Power Market the ISO/RTOs also manage the wholesale power markets in which competitive generation is bought and sold.

The following are the ISO/RTOs that have been created in the United States:

Map of the ISOs in North America
Source: ferc.gov

The utilities in the Southeast, the Northwest and the Southwest (other than California) have not joined ISO/RTOs and continue to both own and operate their own high voltage transmission facilities.  

The following video, prepared by the California ISO/RTO, describes the ISO/RTO responsibilities with respect to operation of their respective portion of the electric transmission grid.

The FERC treats the ISO/RTOs as the providers of all transmission service on their respective portion of the electric transmission grid. The ISO/RTOs are, therefore, responsible for ensuring that transmission is provided on a non-discriminatory basis, as required by the Open Access Orders. The ISO/RTOs also collect all charges for providing transmission service on their portion of the grid. They distribute those revenues (other than those required for internal operations) to the utility owners of the high voltage transmission facilities. That distribution ensures that each utility continues to recover their regulatorily determined revenue requirement. See Post entitled Determining Just and Reasonable Electric Rates for an explanation of regulatory ratemaking.

Multiple Entities Control the Grid

Therefore, the answer to the question of who controls the electric transmission grid has three parts:

  • First, the utilities still own the high power transmission lines that make up the electric transmission grid. They are responsible for maintaining those facilities and keeping them in good working order.
  • Second, in most parts of the country the ISO/RTOs are responsible for directing the operation of the electric transmission grid and for long term planning.
  • Third, the NERC, through FERC, is responsible for ensuring that the utilities operate and maintain their facilities in compliance with mandatory reliability standards.

Author

I. David Rosenstein worked as a consulting engineer and attorney in the electric industry for 40 years. At various times during his career he worked for utility customers, Rural Electric Cooperatives, traditional investor owned regulated utilities and deregulated power generation companies. Each of his posts in this blog describes a different aspect of the past, present or future of the electric industry. 

Leave a Reply